Apartments

Replacing windows in an apartment in the Netherlands: VvE, permits and costs

Updated 8 min read By

Apartment building with new uPVC windows in the same colour

In short

  • In most Dutch apartment buildings the facade and window frames are common property, so you need approval from the owners association (VvE).
  • Check the deed of division and the regulations first; they say who owns the frames and how decisions are made.
  • A permit is usually not needed, except in a protected townscape, for a listed building or when the appearance changes.
  • Four new windows for an average apartment cost about €5,527 to €6,114 including installation and VAT; owner-occupiers who pay themselves can claim the ISDE.

Replacing the windows of a house is mostly a matter of choosing and ordering. In an apartment it is different. The window frames are part of a facade you share with your neighbours, and in the Netherlands that means the owners association, the VvE (Vereniging van Eigenaars), usually has a say. Many international owners only find this out after they have ordered. This guide explains who owns what, how to get approval, which rules apply, and what it costs, so you can plan it properly.

Who owns the window frames?

Every Dutch apartment building with separately owned apartments has a deed of division (splitsingsakte) and regulations (splitsingsreglement), registered at the Land Registry (Kadaster). They define which parts of the building belong to you alone and which are common parts managed by the VvE. There are three common situations:

SituationWho decidesWho pays
Frames are common parts (most common)The VvEThe VvE, from the reserve fund, unless the regulations say otherwise
Frames belong to the apartment, but the facade is commonYou, within the VvE rules on appearanceYou
Frames belong to the apartment, no rules on appearanceYouYou

Under article 5:126 of the Dutch Civil Code the VvE manages the common parts and keeps a reserve fund for costs outside the normal yearly maintenance. For residential buildings the VvE reserves at least the amount from a multi-year maintenance plan (meerjarenonderhoudsplan, MJOP), or at least 0.5% of the rebuilding value each year. If the frames are common parts, they are probably already on that plan with a year and a budget.

You can request the deed and regulations from your VvE manager, your notary, or online from the Kadaster for a small fee. The house rules (huishoudelijk reglement) often add details such as allowed colours, working hours and how to use the stairwell during works.

Getting VvE approval, step by step

  1. Read the deed and regulations. Find out whether the frames are common or private, and what the regulations say about changes to the facade.
  2. Check the maintenance plan. If the VvE plans to replace all frames in two years, replacing yours now may be a waste, or the VvE may contribute.
  3. Talk to the board or the VvE manager first. An informal check saves a lot of time. Ask whether there is an existing standard for colour and layout.
  4. Prepare a short proposal: what you want to replace, the specification (profile, colour inside and outside, layout, glass, ventilation), photos of the current situation, a quote and a planning. A window schedule helps; our installers make one when they measure.
  5. Get a decision. Depending on the regulations the board can approve it, or it goes to the general meeting (ALV). Ask for the approval in writing, by email or in the minutes.
  6. Order after approval. We are happy to quote before the decision, but we only produce once you have the go-ahead.

In small buildings the VvE is sometimes inactive (a slapende VvE). Legally it still exists and decisions still need the other owners. In that case, ask the other owners for written consent; it is usually quick when you propose the same colour and layout as now.

One standard for the whole building

A facade in which every window looks slightly different quickly looks untidy, and that is why most VvEs insist on a standard. If your VvE has none yet, propose one that others can follow later:

ChoiceWhat to fix
Material and profileuPVC, timber or aluminium; the same visible profile width
ColourOutside colour per facade; the inside colour can be free
LayoutThe same division and opening sashes per position in the facade
GlassHR++ or triple; frosted glass in bathrooms; laminated glass where needed
VentilationTrickle vents (ventilation grilles) yes or no, per position
Balcony doorsOpening inwards or outwards, threshold height

uPVC frames can be made in almost any colour, including wood grain finishes, so matching an existing facade is rarely a problem. See the colours on our window frames page.

Do you need a permit?

Replacing windows in the same opening with a similar appearance is usually permit-free in the Netherlands. You do need an environmental permit (omgevingsvergunning) for a listed building (rijksmonument or gemeentelijk monument), and often in a protected townscape (beschermd stadsgezicht) when you change the look of the street-facing facade. Many inner-city apartments in Amsterdam, The Hague, Utrecht, Leiden or Haarlem are in such an area. Check your address in the Omgevingsloket permit check. The VvE approval and the permit are separate: you may need both.

Ventilation and the building rules

The Dutch building rules (Besluit bouwwerken leefomgeving, BBL) say that when you renovate an existing building, you may not fall below the level that was legally there before. For windows this mainly concerns ventilation. If your old frames have trickle vents, or your apartment relies on opening windows for fresh air, the new frames must provide at least the same. New airtight windows without vents in an apartment without mechanical ventilation can lead to condensation and mould. We advise on this at the measuring visit and can fit self-regulating ventilation grilles in the top of the frame.

Upper floors: access, scaffolding and house rules

  • Access: we carry frames up through the stairwell or lift where they fit. Large living room frames or balcony doors sometimes do not fit in the lift; then we bring them in from outside.
  • Scaffolding: for upper floors we often need a mobile scaffold or tower to work safely on the outside. When needed we charge €181.50 incl. VAT for it.
  • Crane or hoist: only if measuring shows it is needed, for example for a heavy lift and slide door on a high floor, and always agreed with you beforehand.
  • House rules: we stick to the working hours in the house rules, protect the stairwell and lift, and take the old frames away the same day.
  • Neighbours: let them know a few days in advance. Removing an old frame is noisy for an hour or two per window.
  • Older buildings: in buildings from before 1994, panels under windows or old putty may contain asbestos. If in doubt, the VvE should have it inspected before the work starts.

What it costs

A typical apartment has a wide living room window, a kitchen window and two bedroom windows. These are our prices for that combination, incl. 21% VAT, in white with HR++ glass:

Apartment, 4 windowsBasicComfortPremium
3-section living room window 240 × 140, fixed + tilt and turn 160 × 130, two tilt and turn 100 × 120€2,744€3,153€3,331
Installation, 4 × €695.75€2,783€2,783€2,783
Total incl. VAT€5,527€5,936€6,114

Basic is a 65 mm profile, fine for a storage room but on the light side for living spaces. Most apartment owners choose Comfort (Aluplast Ideal 7000 NL, 84 mm) or Premium with triple glass. A balcony door is quoted on request, because sizes and opening directions differ a lot between buildings. Installation includes measuring on site, removing and disposing of the old frame, fitting and adjusting the new one, insulating and sealing, and uPVC finishing strips inside. Plastering and painting are not included. Scaffolding, if needed, comes on top. More examples are in what new windows cost in the Netherlands.

Subsidy for apartment owners

If you live in the apartment yourself and pay for the windows yourself, you can claim the ISDE for your apartment: €111 per m² for triple glass in new frames or €25 per m² for HR++, from 3 m². The four windows above add up to about 8 m² including frames, which is €888 with triple glass or €200 with HR++. If the VvE commissions and pays for the work, the VvE can use its own scheme, the SVVE. If you rent the apartment out, the landlord scheme SVOH applies. Read the details in our ISDE subsidy guide.

When the VvE replaces all windows

Replacing all frames in a building at once is usually cheaper per apartment and gives a uniform facade. It does need more preparation: a decision in the general meeting, a budget from the reserve fund or a special contribution, and a planning per apartment. We supply complete buildings anywhere in the Netherlands. Each apartment is measured separately, because openings in the same building often differ by a few millimetres, and everything goes into one window schedule with the apartment number in the first column. We deliver per block and install one apartment at a time, usually in a day.

If you rent

Many international residents rent before they buy. As a tenant you cannot replace the windows yourself: the frames are part of the building and the landlord's responsibility. What you can do depends on the problem.

SituationWho is responsibleWhat you can do
Draught, rot, broken glass, a window that will not closeThe landlord (major maintenance and defects)Report it in writing with photos and ask for a repair date
Landlord does not respondThe landlordSocial housing and regulated rent: go to the Rent Tribunal (Huurcommissie) for a temporary rent reduction; free sector: ask a legal adviser
Small things: oiling hinges, cleaning drainage holes, replacing a broken handleUsually the tenant (minor maintenance)Do it yourself or ask the landlord
You want better insulation but nothing is brokenNobody is obligedAsk the landlord; landlords can use the SVOH subsidy and a better energy label raises the value of the home
The landlord replaces all windows in a renovationThe landlordA renovation proposal needs the consent of at least 70% of tenants in complexes of ten or more homes; you may get a rent increase for the improvement

Replacing windows that are worn out counts as maintenance, for which the landlord does not need your consent and may not raise the rent. Replacing good windows by better ones is an improvement, and then a reasonable rent increase can be agreed. Living in a rented home with very draughty windows? A simple, removable solution such as secondary glazing film or draught strips is allowed without permission, and does not change the building.

Are you the landlord, for example because you bought a house as an expat and now rent it out? Then the ISDE does not apply, but the SVOH scheme for landlords does, and new windows help with the minimum energy label that rented homes must meet. We quote landlords in English too.

Common mistakes

  • Ordering before approval. Without VvE approval you may have to undo the work at your own cost.
  • A different colour or layout. Even small differences in profile width or colour stand out in a facade.
  • Forgetting ventilation. Airtight windows without vents can cause condensation and mould.
  • Ignoring the maintenance plan. If the VvE replaces everything in a year or two, wait or coordinate.
  • No scaffolding in the budget. For upper floors, ask whether it is included.

This guide is general information, not legal advice. What applies to your apartment is in your deed of division and regulations.

Frequently asked questions

Do I need VvE permission to replace my windows?

In most buildings yes, because the facade and window frames are common parts managed by the VvE. Check the deed of division and regulations; even if the frames are yours, the VvE usually has rules on appearance.

Who pays for new windows in an apartment building?

If the frames are common parts, the VvE pays from the reserve fund. If they belong to the apartment, the owner pays. The deed of division decides.

Do I need a permit for new windows in my apartment?

Usually not, unless the building is listed, lies in a protected townscape and you change the street-facing facade, or the appearance changes significantly. Check your address in the Omgevingsloket.

Can I get subsidy for new windows in my apartment?

Yes. As an owner-occupier who pays for the windows yourself you can claim the ISDE: €111 per m² for triple glass in new frames or €25 per m² for HR++, from 3 m². A VvE that pays can use the SVVE.

How long does it take to replace the windows of an apartment?

Installation usually takes one day. Production takes 2 to 6 weeks after measuring. The VvE approval is often the slowest step, so start there.

Can you replace windows on the third floor or higher?

Yes. We work with a mobile scaffold where needed and, only if measuring shows it is necessary, a hoist or crane, always agreed with you in advance.

More guides

Read next

Ready for new windows and doors?

Get a free quote in English within one working day. We measure and install anywhere in the Netherlands.